Rauch Hungária Kft. implemented a new wastewater treatment plant construction investment during 2008-2009. A contract was signed with Inwatech Környezetvédelmi Kft. for the implementation of this investment in the main company.
With the investment, a biological wastewater treatment facility with a hydraulic capacity of 1,000 m3d and a load of 3,500 kg COD/d, 2,500 kg BOI5/d and a capacity of 40,000 LEU was created.
The wastewater treatment plant was designed, licensed, fully constructed, commissioned and commissioned by the main contractor Inwatech Környezetvédelmi Kft.
After the successful technical handover, Rauch Hungária Kft. entrusted Inwatech Környezetvédelmi Kft. with the professional operation of the sewage plant, which we are currently carrying out continuously.